Fervo 500 MW Cape Station under construction; -$87.7M H1 net loss
Filed August 13, 2026 · Period ending June 30, 2026 · ~2 min read
Key Changes
-
high
Subsequent event: Management has evaluated subsequent events that occurred after the date of the Condensed Consolidated Balance Sheets through the date the financial statements were issued.
Notes: Subsequent Events verify on EDGAR → -
high
Cash and equivalents rose to (Jun 2026), funding Cape Station construction and development pipeline.
MD&A: IPO and Liquidity verify on EDGAR → -
high
Cape Station (500 MW under construction) targets first power Q4 2026 and ~100 MW operational Q1 2027. Phase I permitting nearly complete (79/80); Phase II in progress (82/179). Missing commercial operation dates triggers liquidated damages; six-month delay allows PPA termination.
MD&A: Cape Station Progress; Risk Factors verify on EDGAR →
3 more material changes behind this preview — plus the full narrative summary, section-by-section diffs against the prior filing, and verbatim quotes with EDGAR citations.
Want to see a complete report first? Today's free report (WKC 10-Q) is open in full — no account needed.
Partner
Trade FRVO commission-free
Open an account, get a free stock.
Investing involves risk. Free stock terms apply.
Thanks — your feedback helps us improve report quality.
Figures/quotes linked to EDGAR · Narrative written by AI · Aug 14, 2026 · How we verify