Get filing alertsFermi signs $6.5B TensorWave lease, raises $431M via convertible notes, appoints new CEO
Filed August 13, 2026 · Period ending August 13, 2026 · ~2 min read
Key Changes
-
high
Signed first anchor customer TensorWave to 15-year lease generating $6.5B revenue over contract life for 222 MW at Project Matador, with expansion options to triple footprint; phased delivery begins 2H 2027.
Exhibit 99.1 view on EDGAR → -
high
Entered strategic alliance with Hillcore Energy to add 2.6 GW generation capacity at Project Matador with zero capital or debt from Fermi; Hillcore finances and operates under 20-year PPA, Fermi holds acquisition option after year 10.
Exhibit 99.1 view on EDGAR → -
high
Raised $431M via 5.00% convertible senior notes due 2031 with $9.52 initial conversion price; capped call transactions eliminate dilution up to $14.64 per share (100% premium to July 9 closing price).
Exhibit 99.1 view on EDGAR → -
high
Appointed Lee McIntire as CEO to lead transition from development to construction; brings 40+ years experience building large-scale generation and nuclear projects at Bechtel, CH2M Hill, and TerraPower.
Exhibit 99.1 view on EDGAR → -
medium
Q2 2026: $26M net loss ($0.04/share) on $27M G&A expense; invested $185M in PP&E bringing total to $1.55B; cash $92M, debt $520M; remains pre-revenue in development phase.
Exhibit 99.2 view on EDGAR →
Summary
Fermi announced a transformative quarter marked by its first commercial customer agreement and significant capital raise. The company signed TensorWave to a 15-year binding lease generating $6.5 billion in revenue for 222 MW of power at Project Matador, with expansion options that could triple the footprint to approximately 650 MW.
This validates Fermi's business model of providing large-scale, reliable power for AI infrastructure and establishes a revenue foundation as the company transitions from development to operations.
Fermi simultaneously expanded its generation capacity through a strategic alliance with Hillcore Energy that adds 2.6 GW of combined-cycle power at Project Matador, doubling planned on-site generation to 4.8 GW within approximately 30 months. Critically, Hillcore finances, constructs, and operates the facility with no capital or debt commitment from Fermi, which serves as anchor offtaker under a 20-year power purchase agreement and holds an option to acquire the facility at fair market value after year 10. This structure allows Fermi to scale capacity without upfront capital deployment. The company raised $431 million through convertible senior notes due 2031 with a 5.00% coupon and capped call protection that eliminates shareholder dilution up to $14.64 per share. Fermi appointed Lee McIntire as CEO to lead execution through construction and first power, bringing over 40 years of experience building large-scale generation and nuclear projects. The company remains pre-revenue with a Q2 net loss of $26 million driven by $27 million in G&A expense, while investing $185 million in property, plant, and equipment.
Section-by-Section Diff
Event · Item 2.02 — Results of Operations and Financial Condition
Fermi Inc. announced Q2 2026 financial results via earnings release and investor presentation, with conference call scheduled.
Added in current filing · verify on EDGAR →
On August 13, 2026, Fermi Inc. (the “Company”) issued its earnings release announcing its financial results for the second quarter ended June 30, 2026.
The company disclosed its second quarter 2026 financial results through an earnings release. The 8-K does not contain the actual financial figures; those are in the attached exhibits (99.1 and 99.2), which are not included in the body text provided.
Added in current filing · verify on EDGAR →
The Company is hosting a conference call on August 13, 2026 at 8:00 am CT / 9:00 am ET to discuss its financial results for the second quarter ended June 30, 2026.
Management scheduled a conference call for August 13, 2026 at 8:00 am Central Time (9:00 am Eastern Time) to discuss the Q2 2026 results with investors and analysts.
Event · Exhibit 99.1
Fermi announced Q2 2026 results, signed its first anchor customer (TensorWave, $6.5B 15-year lease), appointed a new CEO, and raised $431M via convertible notes.
Added in current filing · view on EDGAR →
Earlier this week, the Company announced that it has signed a 15-year turnkey binding lease agreement with TensorWave, a premier Neocloud provider positioned in the heart of the AI infrastructure ecosystem, to become the first customer at the Project Matador campus. Phase one of the agreement includes 222 MW of total facility power, with total revenue of approximately $6.5 billion over the life of the contract. The agreement also includes two expansion options for TensorWave to triple the size of its footprint on the site over time.
Fermi signed its first anchor customer, TensorWave, to a 15-year binding lease agreement for 222 MW of power at Project Matador. The contract generates approximately $6.5 billion in total revenue over its life and includes two expansion options that could triple TensorWave's footprint. This is Fermi's first commercial customer agreement and validates its business model of providing large-scale, reliable power for AI infrastructure.
Added in current filing · view on EDGAR →
The Board of Directors also appointed Lee McIntire as Chief Executive Officer to lead Fermi’s transition from development into construction and first power. With more than 40 years of experience across Bechtel, CH2M Hill, and TerraPower, McIntire has built large-scale natural gas generation projects, nuclear programs from advanced reactor development through commercial execution, and civil mega-projects on the scale of the Panama Canal expansion. Having served on Fermi's Board as an independent director since September 2025,
he combines this strong track record of execution with his direct knowledge of the Company's assets, partners, and strategy.
Fermi appointed Lee McIntire as CEO to lead the company's transition from development to construction and first power. McIntire brings over 40 years of experience building large-scale natural gas generation projects, nuclear programs, and civil mega-projects, and has served on Fermi's Board since September 2025. This leadership appointment positions the company for its next phase of execution.
Added in current filing · view on EDGAR →
On August 11, the Company announced a build-own-operate-transfer strategic alliance with Hillcore Energy Capital Corporation (“Hillcore”) for approximately 2.6 GW of incremental power generation at Project Matador. The framework agreement would double planned on-site generation to 4.8 GW within approximately 30 months when combined with Fermi's own power generation program.
Under the agreement, Hillcore and its partners will finance, construct, own, and operate their facility under a long-term ground sublease at the Project Matador site, with Fermi committing no capital and issuing no debt for the plant. First power of approximately 350 MW is targeted within 24 months of notice to proceed, with subsequent blocks triggered only by contracted end-user demand and each power purchase agreement term matched to the corresponding customer lease – linking generation buildout to signed commercial demand rather than forecasts. Fermi will serve as anchor offtaker under a 20-year power-purchase agreement and holds an option to acquire the facility at fair market value after year 10.
Fermi entered a strategic alliance with Hillcore Energy to add approximately 2.6 GW of power generation at Project Matador, doubling planned on-site generation to 4.8 GW within approximately 30 months. Hillcore will finance, construct, own, and operate the facility with no capital commitment or debt issuance from Fermi. Fermi will be the anchor offtaker under a 20-year power purchase agreement and holds an option to acquire the facility at fair market value after year 10. This structure allows Fermi to expand capacity without upfront capital deployment.
Added in current filing · view on EDGAR → · paraphrased
Subsequent to quarter end, the Company issued more than $431 million of 5.00% Convertible Senior Notes due 2031, including the full exercise of the initial purchasers' option for an additional $56.3 million. Net proceeds were $416.8 million, before the approximately $34.5 million cost of capped call transactions. Initial conversion price of approximately $9.52 per share. Capped call transactions eliminate shareholder dilution up to an effective strike price of $14.64 per share - representing a 100% premium to the July 9, 2026, closing price.
Fermi raised more than $431 million through 5.00% Convertible Senior Notes due 2031, generating net proceeds of $416.8 million before capped call costs. The notes have an initial conversion price of approximately $9.52 per share. Capped call transactions protect shareholders from dilution up to $14.64 per share, a 100% premium to the July 9, 2026 closing price. The notes carry no scheduled amortization and no financial maintenance covenants, preserving operational flexibility.
Added in current filing · view on EDGAR → · paraphrased
$91.7 million of total cash and restricted cash on hand. $185.0 million of capital invested in Property, Plant, and Equipment, bringing the gross balance to approximately $1.55 billion. Fermi remains focused on disciplined capital deployment matched to commercial progress. $520.1 million of outstanding debt, reflecting a $98.8 million net increase in borrowings under equipment financing facilities. $25.8 million net loss, or $0.04 per basic and diluted share. General and administrative expenses of $26.8 million drove most of that result.
Fermi reported a Q2 2026 net loss of $25.8 million, or $0.04 per share, driven primarily by $26.8 million in general and administrative expenses. The company invested $185.0 million in property, plant, and equipment during the quarter, bringing the gross balance to approximately $1.55 billion. Cash and restricted cash totaled $91.7 million, while outstanding debt reached $520.1 million, reflecting a $98.8 million net increase in equipment financing. Fermi remains pre-revenue and in its development phase.
Event · Exhibit 99.2
Fermi Inc. disclosed Q2 2026 results, a $6.5B TensorWave lease, a 2.6 GW Hillcore power alliance, $431M convertible debt, and CEO appointment.
Added in current filing · view on EDGAR →
$6.5B Phase 1 Contracted Revenue ... 222 MW Phase 1 Contracted Capacity ... Up to ~650 MW Total Facility Power Including Two Data Center Expansion Options ... 15-Year Initial Term with Two 5-Yr. Extension Options ... 2H 2027 Phased Delivery Begins
Fermi signed its first binding customer agreement with TensorWave for $6.5 billion in Phase 1 contracted revenue. The deal covers 222 MW of power capacity initially, with options to expand to approximately 650 MW total. The initial term is 15 years with two 5-year extension options, and phased delivery begins in the second half of 2027.
Added in current filing · view on EDGAR →
2.6 GW Combined-cycle capacity owned by Hillcore ... 4.8 GW Total planned on-site generation within ~30 months ... 350 MW First power targeted within 24 months of NTP ... $0 Fermi capital or debt for the plant ... Hillcore and its partners finance, construct, own, and operate the facility ... Fermi commits no capital and issues no debt ... Fermi is the anchor offtaker under a 20-year PPA, renewable in 10-year increments ... Fermi holds an option, not an obligation, to acquire the facility at fair market value after year 10
Fermi entered a build-own-operate-transfer alliance with Hillcore to add 2.6 GW of combined-cycle generation capacity at Project Matador, bringing total planned on-site generation to 4.8 GW within approximately 30 months. Hillcore finances, constructs, owns, and operates the facility with no capital or debt commitment from Fermi. Fermi is the anchor offtaker under a 20-year power purchase agreement renewable in 10-year increments, with an option to acquire the facility at fair market value after year 10. First power is targeted within 24 months of notice to proceed.
Added in current filing · view on EDGAR → · paraphrased
Upsized Amount $431MM ... Maturity Year 2031 ... Conversion Price1 $14.64 ... Fixed Coupon 5.00% ... $417MM net proceeds ... Capped call limits dilution until a 100% premium to the closing price is achieved ... Reference Closing Price $7.32 ... Base Conversion Price / +30% $9.52 ... Capped Call Strike Price / +100% $14.64
Fermi issued $431 million of convertible senior notes due 2031 with a 5.00% fixed coupon and net proceeds of approximately $417 million. The notes have an initial conversion price of approximately $9.52 per share (30% premium to the $7.32 reference closing price). Fermi entered into capped call transactions with an effective conversion price of $14.64 per share, representing a 100% premium to the closing price, which limits dilution until the stock doubles.
Added in current filing · view on EDGAR →
Lee McIntire Chief Executive Officer ... Fermi Board Member since September 2025 ... 40+ years of leadership in large-scale, complex construction and engineering projects at Bechtel, CH2M Hill, and TerraPower
Fermi appointed Lee McIntire as Chief Executive Officer. McIntire has been a Fermi board member since September 2025 and brings over 40 years of leadership experience in large-scale, complex construction and engineering projects at Bechtel, CH2M Hill, and TerraPower.
Added in current filing · view on EDGAR →
$520MM Debt, Net ... $1.55B Total PP&E, Net Invested $185MM into PP&E in the Quarter ... $92MM Cash and Restricted Cash ... $49MM Cash Used in Operations ... $27MM Total G&A Expense ... $0.04 Net Loss per Share Net Loss of $26MM
For Q2 2026, Fermi reported net debt of $520 million, total property, plant, and equipment of $1.55 billion (having invested $185 million in PP&E during the quarter), and cash and restricted cash of $92 million. The company used $49 million in operations, incurred $27 million in general and administrative expenses, and reported a net loss of $26 million, or $0.04 per share.